Rocky Mountain National Park extends construction timeline at east entrance

Kyle McCabe
Sky-Hi News
Orange barrels sit around a booth at the Fall River Entrance to Rocky Mountain National Park during construction in April 2023.
Rocky Mountain National Park/Courtesy photo

Construction at the Fall River Entrance on the east side of Rocky Mountain National Park will not finish in June as originally expected, instead lasting until late fall, according to a park news release.

The entrance on U.S. Highway 34 saw construction begin in November, but unexpected site conditions and utility coordination challenges since then have pushed back the expected competition date.

During construction, the entrance will have one lane entering the park and one lane exiting the park open. The Fall River Visitors Center, Rocky Mountain Conservancy Nature Store, Gateway Gift Shop and Trailhead Restaurant near the entrance will remain open.



The Fall River Entrance is one of two entrances on the east side of Rocky, the other being the Beaver Meadows Entrance. The park news release states park visitors should expect extended wait times at both entrances.

Rocky’s original design for the Fall River Entrance looked to accommodate around 1.5 million annual visitors, but in the nearly 60 years since, attendance has risen to around 4.5 million visitors per year. The construction project aims to reduce traffic congestion and improve working conditions for park employees.



This story is from SkyHiNews.com.


Support Local Journalism

Support Local Journalism

As a Summit Daily News reader, you make our work possible.

Summit Daily is embarking on a multiyear project to digitize its archives going back to 1989 and make them available to the public in partnership with the Colorado Historic Newspapers Collection. The full project is expected to cost about $165,000. All donations made in 2023 will go directly toward this project.

Every contribution, no matter the size, will make a difference.